Karnali, Dec 10: With the completion of the second phase of works related to the Bheri-Babai Multi-purpose Diversion Project, the third phase of works has begun.
The second phase of work was related to civil construction while the third phase includes work related to hydro-mechanical (HM) and electro-mechanical (EM), according to the information officer at the Project, Lekhnath Subedi.
The national pride project with an estimated cost of over Rs 36.8 billion has achieved 49 per cent of physical progress and 38.24 per cent of fiscal progress so far, shared Subedi.
Agreement for the HM-related works has been inked while e-bidding for EM is in the process, he informed.
The project aims to divert water from Bheri River to Babai River and irrigate 51,000 hectares of farmland in Banke and Bardiya districts through a 12.2-kilometer tunnel.
The multipurpose project, expected to be completed by 2023 will also generate 48 megawatts of electricity, according to the Project.
Do not make expressions casting dout on election: EC
14 Apr, 2022CM Bhatta says may New Year 2079 BS inspire positive thinking
14 Apr, 2022Three new cases, 44 recoveries in 24 hours
14 Apr, 2022689 climbers of 84 teams so far acquire permits for climbing various peaks this spring season
14 Apr, 2022How the rising cost of living crisis is impacting Nepal
14 Apr, 2022US military confirms an interstellar meteor collided with Earth
14 Apr, 2022Valneva Covid vaccine approved for use in UK
14 Apr, 2022Chair Prachanda highlights need of unity among Maoist, Communist forces
14 Apr, 2022Ranbir Kapoor and Alia Bhatt: Bollywood toasts star couple on wedding
14 Apr, 2022President Bhandari confers decorations (Photo Feature)
14 Apr, 2022