By Amar Raj Naharki, Tanahun, Oct. 14: The construction works of the Tanahun Hydropower Project are going on in full swing even during the Dashain.
According to the Project, the workers have been deployed despite the holidays for the construction of the tunnel and transmission line.
Achyut Babu Ghimire, project chief, said, "A total of 160 Nepali and 55 Chinese technicians are currently deployed by the Chinese Sino Hydro Company for the construction of the tunnel under package-2 of the project."
He added that 75 workers were on the field for the construction of the transmission line.
Even the prohibitory order imposed from May due to the COVID-19 pandemic had not stopped the construction of Tanahun Hydel Project. The workers were deployed on the construction site by ensuring that all the health and safety standards were followed.
The project, once completed, is expected to produce 140 MW of electricity. The government has prioritised the completion of the project as it would reduce the shortage of electricity during the winter season.
"The completion of the project has been prioritised as it would end the trend of importing electricity from India during the winter season," said chief Ghimire.
Photos:
Do not make expressions casting dout on election: EC
14 Apr, 2022CM Bhatta says may New Year 2079 BS inspire positive thinking
14 Apr, 2022Three new cases, 44 recoveries in 24 hours
14 Apr, 2022689 climbers of 84 teams so far acquire permits for climbing various peaks this spring season
14 Apr, 2022How the rising cost of living crisis is impacting Nepal
14 Apr, 2022US military confirms an interstellar meteor collided with Earth
14 Apr, 2022Valneva Covid vaccine approved for use in UK
14 Apr, 2022Chair Prachanda highlights need of unity among Maoist, Communist forces
14 Apr, 2022Ranbir Kapoor and Alia Bhatt: Bollywood toasts star couple on wedding
14 Apr, 2022President Bhandari confers decorations (Photo Feature)
14 Apr, 2022