Lamjung, Dec 19 : The Upper Syange Hydropower Project here has successfully tested 2.4 MW of electricity generation. The power generation test of the project located in Marsyangdi Village Municipality Ward No. 4 Mipra was successful.
The construction of the project was completed in September and testing has been started since December 8. “We have communicated to the Nepal Electricity Authority to connect the generated power to the national grid. Testing of hydromechanical and electromechanical equipment of civil structures and connected equipment has been successful,” said Som Tamang, technician at the project.
The construction of the project was started in 2074 BS.
Technician Tamang informed that the project will be connected to Khudi substation at a distance of 12 km through 33 KV transmission line. The project will generate 14.616 gigawatt hours of electricity annually.
Similarly, the project can generate 2.868 gigawatt hours of electricity in winter and 11.748 gigawatt hours in rainy season. The construction of the project has been completed at a cost of Rs 500 million, according to Upper Syange Hydropower Limited.
Do not make expressions casting dout on election: EC
14 Apr, 2022CM Bhatta says may New Year 2079 BS inspire positive thinking
14 Apr, 2022Three new cases, 44 recoveries in 24 hours
14 Apr, 2022689 climbers of 84 teams so far acquire permits for climbing various peaks this spring season
14 Apr, 2022How the rising cost of living crisis is impacting Nepal
14 Apr, 2022US military confirms an interstellar meteor collided with Earth
14 Apr, 2022Valneva Covid vaccine approved for use in UK
14 Apr, 2022Chair Prachanda highlights need of unity among Maoist, Communist forces
14 Apr, 2022Ranbir Kapoor and Alia Bhatt: Bollywood toasts star couple on wedding
14 Apr, 2022President Bhandari confers decorations (Photo Feature)
14 Apr, 2022