Myagdi, May 14 : Electricity generated from the Mystery rivulet hydropower project constructed in Myagdi’s Annapurna rural municipality-4, Narchyang has been added to the national grid since Thursday.
The 42-MW Mystery rivulet hydro project constructed by the Mountain Energy Nepal had linked its electricity to the national grid through Dana substation.
Project resident engineer Diwakar Khadka shared that the electricity generated from all three units have been added to the central transmission system.
“The power generated from the Mystery rivulet project has been synchronized to the national grid. All the units of the project have been brought into operation for test”.
The Mystery rivulet hydel project is so far the biggest hydro project under construction in Myagdi.
Do not make expressions casting dout on election: EC
14 Apr, 2022CM Bhatta says may New Year 2079 BS inspire positive thinking
14 Apr, 2022Three new cases, 44 recoveries in 24 hours
14 Apr, 2022689 climbers of 84 teams so far acquire permits for climbing various peaks this spring season
14 Apr, 2022How the rising cost of living crisis is impacting Nepal
14 Apr, 2022US military confirms an interstellar meteor collided with Earth
14 Apr, 2022Valneva Covid vaccine approved for use in UK
14 Apr, 2022Chair Prachanda highlights need of unity among Maoist, Communist forces
14 Apr, 2022Ranbir Kapoor and Alia Bhatt: Bollywood toasts star couple on wedding
14 Apr, 2022President Bhandari confers decorations (Photo Feature)
14 Apr, 2022