Khotang, April 28 : The blacktopping of Diktel-Khanidanda-Ahale road – the shortest surface route to connect the eastern Terai districts is not likely to complete in the stipulated tim
The blacktopping of Diktel-Ahale road (10.974-km) that was initiated at the investment of the National Reconstruction Authority (NRA) has only witnessed a physical progress of 48 percent when the stipulated time for the same has exceeded.
The deadline was extended up to May 12 when the contractor company Yakthunghang/Sap/Siruwa JV failed to complete the task of blacktopping in the agreed date of 20 March 2020.
Consultant Engineer Chanchal Kumar Jha said that the physical progress of the blacktopping so far was only 48 percent while financial progress was 47.76 percent. In the fiscal year 2077/78 BS, the financial progress of road blacktopping was 14.23 percent and physical progress 9.14 percent, Engineer Jha informed.
The NRA had initiated the blacktopping of the road from Diktel to Gaighat of Udayapur via Khanidanda airport at the investment of over Rs 210 million.
Do not make expressions casting dout on election: EC
14 Apr, 2022CM Bhatta says may New Year 2079 BS inspire positive thinking
14 Apr, 2022Three new cases, 44 recoveries in 24 hours
14 Apr, 2022689 climbers of 84 teams so far acquire permits for climbing various peaks this spring season
14 Apr, 2022How the rising cost of living crisis is impacting Nepal
14 Apr, 2022US military confirms an interstellar meteor collided with Earth
14 Apr, 2022Valneva Covid vaccine approved for use in UK
14 Apr, 2022Chair Prachanda highlights need of unity among Maoist, Communist forces
14 Apr, 2022Ranbir Kapoor and Alia Bhatt: Bollywood toasts star couple on wedding
14 Apr, 2022President Bhandari confers decorations (Photo Feature)
14 Apr, 2022