Myagdi, Jan 3 : The construction of the 220 VK Dana-Khurkot Sub-station and transmission line under the Kaligandaki corridor has been completed in Myagdi.
Two sub-stations have been constructed at Dana of Myagdi and Khurkot of Parbat while 110 towers and 39.6 km of power cables have been installed.
The infrastructure development and equipment installation work have been completed, and now we are working on substation charge and testing, said the project's assistant manager Laxman Phunyal.
The substation and transmission line will come into operation within the next 15 days.
The project began in 2016 with the support of the Asian Development Bank. The project implemented by the Nepal Electricity Authority was completed two years later than scheduled.
The total cost of the project to be completed in 2018 was Rs. 2.9 billion but it cost almost Rs. 3 billion as a result of the delay.
The completion of the project now ensures the connection of the power produced from hydropower projects in Kaligandaki and its tributaries and the projects in Mustang to the national grid, chief of the project Chandan Kumar Ghosh said.
The delay in the project was due to issues related to land encroachment, distribution of compensation, acquisition of forest land, and floods and landslides, claimed Ghosh.
Do not make expressions casting dout on election: EC
14 Apr, 2022CM Bhatta says may New Year 2079 BS inspire positive thinking
14 Apr, 2022Three new cases, 44 recoveries in 24 hours
14 Apr, 2022689 climbers of 84 teams so far acquire permits for climbing various peaks this spring season
14 Apr, 2022How the rising cost of living crisis is impacting Nepal
14 Apr, 2022US military confirms an interstellar meteor collided with Earth
14 Apr, 2022Valneva Covid vaccine approved for use in UK
14 Apr, 2022Chair Prachanda highlights need of unity among Maoist, Communist forces
14 Apr, 2022Ranbir Kapoor and Alia Bhatt: Bollywood toasts star couple on wedding
14 Apr, 2022President Bhandari confers decorations (Photo Feature)
14 Apr, 2022