Damauli, Sept 19 : The construction works for Tanahu Hydropower Project transmission line have begun here. The works began under the third package of the project.
The transmission line will be of 220 KV double circuit, said project chief Achyut Ghimire, adding that the double circuit transmission line will be built from Damauli to Bharatpur. An Indian company KEC has been contracted for the construction.
He further said digging for base for first tower was over and the works now onward would be intensified. There will have a total of 30 towers. The works to the project were however affected earlier owing the COVID-19 menace.
The construction of the transmission lined is expected to complete by 2022 March. The poles for the transmission line have been brought near Indian border. Ghimire believed that the remaining activities would be accelerated in the winter season.
Some 7,923 trees need to be cut down in Tanahu while the study on it was underway on the part of Chitwan. Even the works for power house are going on under the second package of the project. The power house is being built at Jhaputar of Rishing Rural Municipality-1.
Do not make expressions casting dout on election: EC
14 Apr, 2022CM Bhatta says may New Year 2079 BS inspire positive thinking
14 Apr, 2022Three new cases, 44 recoveries in 24 hours
14 Apr, 2022689 climbers of 84 teams so far acquire permits for climbing various peaks this spring season
14 Apr, 2022How the rising cost of living crisis is impacting Nepal
14 Apr, 2022US military confirms an interstellar meteor collided with Earth
14 Apr, 2022Valneva Covid vaccine approved for use in UK
14 Apr, 2022Chair Prachanda highlights need of unity among Maoist, Communist forces
14 Apr, 2022Ranbir Kapoor and Alia Bhatt: Bollywood toasts star couple on wedding
14 Apr, 2022President Bhandari confers decorations (Photo Feature)
14 Apr, 2022