Birgunj, Dec 24 : The task of track opening for electric railway along the Bagmati-Dhansar section in Rautahat district has witnessed progress of late. Engineer at Railway Department Sumod Pokharel told RSS that the contractor company has expedited the job of track opening.
Federal government is spending Rs 3 billion for the development of 23-kilometre track in the district. Along with three link lines, the government is working to build 1003.8 Kms long electric railway along the east-west highway in 10 different packages.
The contractors winning bid for package one to five have agreed to accomplish all the tasks within two and a half years. As part of the same agreement, the contractors have sped up the bridge construction too. A total of six bridges would be constructed along the route in the district.
Similarly, the Division Forest Office, Chandrapur, has written to the Department of Forest seeking its approval for cutting the trees along the Bagmati-Dhansar section in the district for the railway route construction.
Do not make expressions casting dout on election: EC
14 Apr, 2022CM Bhatta says may New Year 2079 BS inspire positive thinking
14 Apr, 2022Three new cases, 44 recoveries in 24 hours
14 Apr, 2022689 climbers of 84 teams so far acquire permits for climbing various peaks this spring season
14 Apr, 2022How the rising cost of living crisis is impacting Nepal
14 Apr, 2022US military confirms an interstellar meteor collided with Earth
14 Apr, 2022Valneva Covid vaccine approved for use in UK
14 Apr, 2022Chair Prachanda highlights need of unity among Maoist, Communist forces
14 Apr, 2022Ranbir Kapoor and Alia Bhatt: Bollywood toasts star couple on wedding
14 Apr, 2022President Bhandari confers decorations (Photo Feature)
14 Apr, 2022