Friday, 26 April, 2024
logo
BUSINESS

Mainahiya-Sampatiya transmission line to complete by mid-July



mainahiya-sampatiya-transmission-line-to-complete-by-mid-july

By A Staff Reporter
Kathmandu, Mar. 21: Around 60 per cent construction work on Mainahiya-Sampatiya 132 kV double circuit transmission line connecting Nepal and Uttar Pradesh (UP) of India has been completed.
Work is moving in full swing to complete the construction of the transmission line from Mainahiya substation of Rupandehi to Sampatiya (New Nautanuwa) substation in Uttar Pradesh, India by mid-July, 2022.

The foundation of 44 of the 96 towers in the 28-kilometer (km) transmission line has been laid, according to Nepal Electricity Authority (NEA).
Five towers have been installed. Compensation for the land in the route of the transmission line has been determined and all required equipment has been brought to the project site.
A team led by Secretary at the Ministry of Energy, Water Resources and Irrigation Devendra Karki, board of directors of NEA and its Managing Director Kul Man Singh visited the construction site of the project on Sunday.

The team instructed the project management to complete the construction work on time as the transmission line is important for power trade between the two countries.
The sixth meeting of the Joint Steering Committee of Energy Secretary level meeting between Nepal and India held in Pokhara in January, 2019, had agreed to construct the New Nautanuwa-Mainahiya 132 kV transmission line between Nepal and Uttar Pradesh.

The decision was made to connect the line to New Nautanuwa (Sampatiya, India) substation. After this, the seventh meeting of the Joint Steering Committee of Energy Secretary level held in Bangalore, India, in November, 2019, decided to connect the transmission line to the substation.
MD Ghising said that 132 kV transmission line was being constructed to facilitate cross border electricity trade as Uttar Pradesh, where structure of only 33 kV transmission line passes through Nepal at present.

"This line is important for Nepal to import power if needed and to export the surplus electricity to UP," Ghising said. "Once completed, 132 kV transmission infrastructure will be ready with UP, which will facilitate and expand electricity trade between the two countries."

The government of Nepal has invested in the project which is estimated to cost around USD 8 million. The transmission line starting from Mainahiya 132 kV substation will be constructed up to Marchwar (Shree Rampur) border point with India.

Hari Pandey, chief of the project, said that two bays and 3-4 towers should be constructed at the substation to connect the line to India.
Pandey said that Nepal had agreed to provide funds for the project and the Indian side had agreed to work.

Butwal-Lumbini transmission line in final stage
The 132 kV double circuit transmission line project under construction from Yogikuti (Butwal) to Mainhiya has reached the final stage. The new line is expected to improve the power supply and control technical leakage in Bhairahawa area of ​​Rupandehi.
The overall construction progress of the project is 95 per cent, the NEA said

Of the 56 towers in the 18-km transmission line, 55 have already been built. Wire stretching work has been completed in around 10 km.
Work is underway to make 2 km of transmission line underground in the Butwal market area.

One of the two 132/33 kV, 45 MVA capacity power transformers to be installed at Mainahiya substation has already been connected.
The remaining 33/11 kV, 16 MVA power transformer is being brought to the project site.